Advertise in Print | Subscriptions
Published July 15, 2014, 11:37 AM

CHS still considering Spiritwood, ND, nitrogen plant

CHS officials have not set a date for a decision on the proposed nitrogen fertilizer plant in Spiritwood, N.D., according to Brian Schouvieller, CHS senior vice president.

By: Keith Norman , Forum News Service

CHS officials have not set a date for a decision on the proposed nitrogen fertilizer plant in Spiritwood, N.D., according to Brian Schouvieller, CHS senior vice president.

“I won’t put a timeline on it,” he says. “But there is a point of time where we make a decision. We won’t be rushed.”

In April, CHS announced a delay in the project, citing rising costs. Plans for the project were originally announced in September 2012, with an estimated cost of about $1.2 billion. Project costs had risen to more than $1.8 billion when the delay was announced.

The project would be the largest construction project for CHS and the largest in North Dakota.

“We’re still looking at the economic viability of the project,” Schouvieller says. “We’re trying to pull costs out and working with the state for funding and incentives.”

Water is another issue.

“… We have not been very active since putting the project on hold,” he says, referring to water testing. “Testing of the Spiritwood Aquifer showed an additional 600 gallons per minute. We need 2,700 gallons per minute. The next place to look is the Jamestown Aquifer. We need to determine how much water is available from that.”

Gray water — treated wastewater — is another option, Schouvieller says.

The Jamestown/Stutsman Development Corp. approved up to $99,000 in funding for phase one testing on the Jamestown Aquifer during its meeting July 14. Costs of complete testing of the aquifer are estimated between $500,000 and $700,000, according to Connie Ova, CEO of the JSDC. The JSDC could look for funding partners for the complete project after phase one is finished.

Ova says funding for the first phase of the project still required approval by the Jamestown City Council and the Stutsman County Commission at their August meetings. She estimates work could start in August.

“We would like to see the water study done in August,” Schouvieller says. “We need assurance there will be an adequate water source. We know there is an adequate water supply either as a combination of the two aquifers (Spiritwood and Jamestown) or from gray water.”

Tags: